Administration Building
Construction

The Administration Building at the main campus is scheduled for renovation beginning January 2007. Measure E funds have allowed for the upgrade of this building. For more information regarding Measure E, please click here. 

Renovation of the building includes new carpet, paint, floors and a heating EMS system. The building will also be evaluated for asbestos abatement compliance as mandated by state agencies.

Asbestos abatement is the process through which asbestos containing building materials are evaluated for integrity to determine whether they should be removed or steps should be taken to minimize the health risks associated with asbestos. Asbestos is abated only when required for renovation, remodeling or maintenance. This usually involves moving ceiling tile, repairing plumbing or anything else that contains asbestos.

The renovation project is scheduled for completion by July 2007. During construction, offices and departments which were housed in this building will be temporarily relocated in areas throughout the college. For a complete listing of temporary office locations, please click here.  For downloadable PDF maps to each individual office, select one of the following that corresponds to the department:

For current updates, click here

Department Maps

Academic Affairs Counseling Center Scheduling Office
Academic Senate Graduation Office Scholarship Office
Administrative Services Mail Room School of Continuing Education
Admissions & Records Office of School & Community Partnership Student Services
Cashier's Office Outreach Transfer Center
College Foundation President's Office Veteran's Office
Community Services Public Affairs  

Maps are forthcoming for the department names which are not highlighted in color above. Please check again soon.  

Phases

The renovation of this building will take place in Phases which include:

  • Phase I through III- Relocation of Offices (The Move)
    • Begins Jan. 8 through Mar. 9, 2007
       
  • Phase  IV - Construction
    • Begins mid March 2007
    • Completion Date is mid July 2007
       
  • Phase V - Re-occupancy of the Building
    • Scheduled for mid July 2007
    • Admission Building is scheduled for July 2007

(This document is subject to change as the best services are provided to students, staff and community members.)

We realize this project may create an inconvenience for our students, staff and community, and we thank you for your patience and continued support. We will make every attempt to expedite the construction and communicate the necessary information. The college is committed to continue to improve the physical aesthetics of our campus to add new character and pride to Santa Ana College.  

For Administration Building construction updates, please select here.  

Please check this site periodically for updated information.  For questions and concerns, please contact Public_Affairs@sac.edu


 

Updated 8/15/07            